home   newsroom     who we are    missions    history    related links     Kids Corner
USACE Home Page Philadelphia District Home Page

Project Links

Questionsquestions Public Affairs
Contact: Ed Voigt

U.S. Army Corps of Engineers
Wanamaker Building,
Room 600
100 Penn Square East
Phila, PA 19107-3390

Phone: 215-656-6515
FAX: 215-656-6820

Security Privacy & Security

External Links

The appearance of hyperlinks does not constitute an endorsement by the US Army Corps of Engineers of the Web site or the information, products or services contained therein.  The US Army Corps of Engineers does not exercise any editorial control over the information you may find at these locations.  Links are provided consistent with the purpose of this DoD Web site.
 

Delaware River Main Stem & Channel Deepening Project

Delaware River Main Channel Deepening Project Map
The Corps' history in dredging the Delaware River federal shipping channel dates back to the late 1800s when the controlling depth of the Delaware River was 18 feet. As ships with deeper drafts evolved, periodic modifications of the channel took place over the years, eventually reaching the current 40-foot depth during World War II. For more than 60 years the Corps' Philadelphia District has maintained the Delaware River at this authorized depth, thus allowing the safe transit of commercial and recreational vessels from Philadelphia to the Delaware Bay.

In 1983, Congress directed the Philadelphia District to begin a study to determine if it was in the federal interest to modify the existing 40-foot Delaware River main shipping channel. In 1987, the study progressed to the feasibility phase where we performed extensive environmental and economic studies. The 1992 final feasibility report recommended to Congress that the channel be deepened to 45-feet and that doing so was environmentally sound, economically justified and technically feasible. Congress supported that recommendation by authorizing the deepening project for construction in 1992.

During the subsequent Preconstruction Engineering and Design (PED) phase, the Corps completed an economic re-evaluation and spent over $7 million in additional environmental analyses, consulting national experts and conducting studies with the close cooperation of the appropriate federal and state environmental agencies. The resulting Supplemental Environmental Impact Statement was circulated for both resource agency and public review in January 1997. After an extended comment period, the document was finalized in July 1997 and once again circulated for public comment in the same year. In May 1998, the Corps held a public hearing, and the transcript from that hearing is a part of the official record for this permit application. In December 1998, the Record of Decision was signed, signifying completion of the National Environmental Policy Act, or NEPA, process.

The Delaware River Main Stem and Channel Deepening will cost approximately $311 million dollars -- with about two-thirds funded by the federal government and the remainder by the Philadelphia Regional Port Authority, the non-federal sponsor. The project is designed to deepen the existing main shipping channel of the Delaware River from 40 feet to 45 feet from Philadelphia Harbor, Pennsylvania and Beckett Street Terminal, Camden, New Jersey to the mouth of the Delaware Bay.

Although this is a total distance of 102.5 miles, 33 miles (mostly in the Delaware Bay) are already at 45 feet or deeper. The project follows the existing 40-foot federal main shipping channel alignment. The existing authorized widths in the straight portions of the channel, ranging from 400 feet in Philadelphia to 1,000 feet in the bay, will not change. However, 12 of the existing 16 bends in the channel will be widened for safer navigation. In addition, the Marcus Hook Anchorage will be deepened to 45 feet.

To deepen the channel, approximately 16.0 million cubic yards of material must be removed during initial construction of the project. Of that amount, approximately 11.9 million cubic yards of sand, silt, and clay will be taken from the river portion of the project -- the area from Philadelphia/Camden to the Upper Delaware Bay. About 77,000 cubic yards of rock will also be removed from the Marcus Hook area of the river.

The material to be dredged from the river portion is slated for placement at existing federal upland Confined Disposal Facilities, or CDFs, in New Jersey and Delaware. While these sites will provide more than adequate long-term capacity, material placed there will also be available for beneficial uses in other locations. For example, several years ago about 150,000 cubic yards of dredged material from the Corps’ National Park, New Jersey CDF was donated to West Deptford Township for use in its River Winds riverfront development project. The Philadelphia Regional Port Authority funded the cost of transporting the material to the site.

The remaining 4.1 million cubic yards is primarily good quality sand from the Delaware Bay. The sand will be dredged and placed for beneficial use at Kelly Island, Delaware for wetland restoration and protection (a similar initiative at Egg Island Point, New Jersey has been deferred pending availability of sufficient sand). It also will be placed along the Delaware Bay coastline for shore protection at Broadkill Beach.

Annual maintenance dredging for the entire project will increase by approximately 860,000 cubic yards per year to approximately 4.3 million cubic yards. The current 40-foot channel requires approximately 3.5 million cubic yards in annual maintenance dredging.

The bulk of dredging will be performed by hopper and hydraulic pipeline dredges with a bucket dredged used for rock removal in the Marcus Hook area.

To ensure that construction of the project does not impact the natural resources of the region, the Corps has set up pre-construction monitoring to establish baseline information that the Corps, DNREC and other state and federal agencies will use to track the ongoing effects of the project. Data is being collected on oysters, horseshoe crabs, shorebirds, blue crabs and sand builder worms. The monitoring will continue during and after project construction.

Additional Links
 

WE WANT TO HEAR FROM YOU!
Help us keep improving our website... Send your questions, problems and comments to the Philadelphia District Web Master

This is an official US Government information system for authorized use only.
It is intended for unclassified, non-sensitive, non-privacy act information.