Home > Missions > Civil Works > Manasquan Inlet to Barnegat Inlet

Construction Status for Northern Ocean County Project

CURRENT BEACHFILL STATUS

  • Location: Mantoloking 
  • Date: 9/19/2018
  • Beach access closures: Lyman Ave
  • Additional info: Dredges RN Weeks left for safe harbor due to storm. Will return when calmer weather conditions allow

  • Location: Seaside Park
  • Date: 9/19/2018
  • Beach access closures: L
  • Additional info: Dredge CR McCaskill was towed to shipyard for repairs. Dredge RS Weeks will replace the CR McCaskill and will arrive when calmer weather conditions allow

Northern Ocean County Coastal Storm Damage Reduction

Project Status

The U.S. Army Corps of Engineers (USACE) awarded a contract to Weeks Marine Inc. to construct the Northern Ocean County dune and berm system. The project is a partnership between USACE and the state of New Jersey. Once the construction is completed, the project is designed to reduce damages to physical infrastructure from the future coastal storms that will impact Northern Ocean County. 

Construction Schedule

USACE's contractor Weeks Marine Inc. will be using multiple dredges to complete the beachfill contract. Three hopper dredges (R.N. WeeksB.E. Lindholm and Magdalen) are expected to be used during construction. Hopper dredges function like a ship as they transit back and forth between a sand borrow site and pump out buoy near the shoreline. Weeks Marine will also be using two pipeline cutter head dredges (EW Ellefsen and C.R. McCaskill), which function more like a stationary barge and continuously pump sand from a sand borrow site through a pipeline and onto the beach. The type of dredge used for each community depends on the distance from the sand borrow site to the shoreline. 

- Schedule Updated: Sept 19, 2018 (check the map to the right to clarify the different sections of the project)

- Note - the schedule is an estimate. Construction could begin sooner or later than the dates listed below based on weather, equipment issues and overall progress. 

 *Mantoloking Northern Area - stretches from Sta. 207 (approx. 2000 ft. north of Herbert St.) to Sta. 162 (municipal boundary with Bay Head).

Dredging Equipment

Community

Hopper Dredge
Magdalen

Toms River North– construction start depends on ongoing progress on Long Beach Island. Work is expected to begin in early October and last through late December of 2018. The plan is to make the pipe landing between East Pompano Way and E Sandpiper Way and first pump North, then flip and pump South.

Bay Head– construction follows Toms River North. Current construction estimate is late December of 2018 to mid-April of 2019. The plan is to make the pipe landing near Mount Street and first pump North, then flip and pump South.

Hopper Dredges
R.N. Weeks and
B.E. Lindholm
(typically work in tandem on same line)

Mantoloking– construction complete in base contract area.

Brick Townshipconstruction began in April and was completed on Aug. 16, 2018. The pipe landing was made near Bel Air Road. Pumping will proceed South first, then flip and pump North.

Mantoloking Northern Area*construction is expected to start on/about 8/25/2018 (following re-pump of southern Mantoloking area). Construction is estimated to last through late November. The plan is to make the pipe landing near Lyman Street and first pump South, then flip and pump North.

Lavallette– construction follows Mantoloking option areas. Current construction estimate is late November through mid-March. Plan is to make the pipe landing near Magee Avenue and first pump North, then flip and pump South.

Point Pleasant Beach-construction follows Lavallette. Current construction estimate is mid-March through mid-April. The plan is to make the pipe landing at Elizabeth and Carter Avenues and first pump to the South then flip and pump North. Work to extend the Sea Avenue ocean outfall will be ongoing from June to late September or early October. Access via Maryland Ave will be modified to allow limited equipment access. Pedestrian access will be maintained. Point Beaches are open except within fenced construction area.

Pipeline Dredge
EW Ellefsen

Toms River South (Ortley Beach)–construction began in mid-July and is estimated to last through late-November. The pipe landing has been made just north of Hiering Ave. From there, contractor will pump North into Ortley.

Seaside Heights– construction follows Ortley Beach. Current construction estimate is late November to early February. The pipe landing will remain at north of Herring Ave. Pipe will be flipped, then pumped South through Seaside Heights.

Pipeline Dredge
RS Weeks (replaces CR McCaskill)

Seaside Park– construction began on Aug. 9 and is estimated to last through late-November. The plan is to make the pipe landing near 5th Ave and first pump North, then flip and pump South.

Berkeley Township– construction follows Seaside Park. Current construction estimate is late-November through early December

Project Background

The Manasquan Inlet to Barnegat Inlet (also known as "Northern Ocean County" project) Coastal Storm Damage Reduction Project is the result of a 2002 feasibility study that investigated flood and coastal storm damage effects between the two inlets. The study involved extensive engineering, environmental, and economic analyses and recommended the construction of a dune and berm system with the intent of reducing impacts from coastal erosion and storms. The plan calls for beachfill construction along the oceanfront between Point Pleasant, New Jersey and the northern boundary of the Island Beach State Park utilizing sand from an offshore borrow source and periodic nourishment for a period of 50 years. The project includes the following municipalities: Point Pleasant Beach; Bay Head; Mantoloking; Brick Township; Toms River Township; Lavallette; Seaside Heights; Seaside Park; and Berkeley Township. Congress authorized the project as part of the Water Resources Development Act of 2007.

Contact Us

Philadelphia District
Public Affairs Office
100 Penn Square E.
Philadelphia, PA 19107
215-656-6515  
Email

Contract Sections

Progress Map (click for more detail)