WHITE HAVEN, PA -- The U.S. Army Corps Engineers’ Philadelphia District updated the 2024 Francis E. Walter Dam recreation plan.
The Army Corps updated the plan, which states whitewater and fisheries releases will be scheduled if enough water storage is accumulated in the reservoir. Currently, there is enough water storage to schedule the following increments:
- 7 – Add fishing releases on Sept. 14-15 (250 cubic feet per second plus inflow, 350 cubic feet per second max).
- 8b – Increase Aug. 24-25 whitewater releases (1700 cubic feet per second on Saturday and 1000 cubic feet per second on Sunday).
It’s important to note that all recreational releases are subject to change based on the potential need for flood control operations.
Release no. 24-028