Home > Missions > Civil Works > Long Beach Island Storm Damage Reduction

Long Beach Island Project Status

Overview

The U.S. Army Corps of Engineers awarded a contract to Weeks Marine to repair and renourish the three sections of the project that were constructed prior to Hurricane Sandy: Harvey Cedars, Surf City and a section of Brant Beach in Long Beach Township. The contract called for the dredging, pumping and placement of sand as well as dune repairs; crossovers and sand fencing repairs; and dune grass plantings. Beaches were widened in front of the dune system. USACE's contractor Weeks Marine Inc. used multiple dredges to complete the beachfill contract. Beachfill operations were completed in October of 2018. 

Dredging Equipment

Community

Completion

Hopper Dredge Magdalen

Brant Beach

Beachfill operations were completed on 5/30/2018.

 Surf City Beachfill operations were completed on 8/6/2018. 

Hopper Dredges
Magdalen and
R.N. Weeks

Harvey Cedars

Beachfill operations were completed on 10/2/2018

 

Long Beach Island Coastal Storm Damage Reduction

Project Background

Long Beach Island is an 18-mile barrier island in southern Ocean County, New Jersey. The area regularly suffers damages from coastal storms, hurricanes and nor'easters. The Barnegat Inlet to Little Egg Inlet Coastal Storm Risk Management project, also known as the Long Beach Island beachfill or beach nourishment program, is designed to reduce erosion and property damages associated with these events. It is a joint effort of the Army Corps and the New Jersey Department of Environmental Protection. 

A Feasibility Report Completed in September of 1999 recommended beachfill with periodic nourishment to reduce potential hurricane and storm damages for the island. The project involves the construction of a dune with a top elevation 22 feet above sea level with a 300-400 foot wide berm, depending on the location of the beach on the island, at an elevation of 8 feet above sea level.

The Long Beach Island Coastal Storm Damage Reduction project was only partially completed when Hurricane Sandy hit the New Jersey shore. The Army Corps completed the initial construction of the project at Surf City in 2006; Harvey Cedars in 2010; and Brant Beach between 31st and 57th Streets in Long Beach Township in 2012. The Army Corps repaired beaches in Surf City and Harvey Cedars in 2012 after Hurricane Irene, and fully restored the beaches within all three communities after Hurricane Sandy in 2013. The restoration and repair work was funded 100 percent through the Army Corps’ Flood Control and Coastal Emergencies program.  On December 5, 2014 the U.S. Army Corps of Engineers awarded a contract to the Great Lakes Dredge and Dock Company, for $128 million to complete initial construction of the Long Beach Island project. Beachfill operations completed in November of 2016. The initial construction was funded entirely by the federal government through the 2013 Disaster Relief Appropriations Act (PL113-2), commonly known as the Hurricane Sandy Relief Bill. The project is eligible for continued periodic nourishment.

Project Photos