CONGRESSIONAL DISTRICT: NJ-3, 4
APPROPRIATION / PHASE: Construction, General
BUSINESS PROGRAM: Flood and Coastal Storm Damage Reduction
LOCATION: The study area is located on the Atlantic coast of Ocean County, New Jersey, extending approximately 14 miles from Point Pleasant Beach to Island Beach State Park, a barrier island wildlife area.
DESCRIPTION: This project was authorized by Section 1001 (32) of the Water Resources Development Act of 2007. The study investigated flood and coastal storm damage effects with a view toward reducing impacts from coastal erosion and storms. The study investigated flood and coastal storm damage effects with a view toward reducing impacts from coastal erosion and storms. The recommended plan calls for construction of a beach fill with a berm and dune along the study area oceanfront utilizing sand from an offshore borrow source and periodic nourishment for a period of 50 years. Initial fill requirements would be about 10 million cubic yards, with periodic nourishment at 4-year intervals with about 1 million cubic yards placed.
PROJECT GOALS: The purpose of this project investigated hurricane and coastal storm damage reduction, and recommendation of a beachfill. With a berm and dune and a periodic nourishment for a period of 50 years.
STATUS: The Chief of Engineers Report was completed in December 2003. This project was authorized in the 2007 Water Resources Development Act (WRDA). After Hurricane Sandy, the Disaster Relief Appropriations Act of 2013 was passed by Congress and signed into law by the President on January 29, 2013 as Public Law 113-2 (Act). The legislation provided supplemental appropriations to address damages caused by Hurricane Sandy and to reduce future flood risk in ways that will support the long-term sustainability of the coastal ecosystem and communities, and reduce the economic costs and risks associated with large-scale flood and storm events. This project was determined to be eligible for P.L. 113-2 2013 Disaster Relief Appropriations Act (Hurricane Sandy) funds as an Authorized but Unconstructed project. The term “authorized but unconstructed project” refers to previously authorized projects for which no physical construction has occurred as well as projects that contain elements where construction has not been completed. In January of 2017, USACE awarded a contract to Weeks Marine Inc. to complete the initial construction of the project. Beachfill operations were completed in the summer of 2019.
Periodic nourishment of the project is expected to begin in 2023.
DATE OF PROJECT PARTNERSHIP AGREEMENT: 18 July 2014
SPONSOR: New Jersey Department of Environmental Protection
TARGET COMPLETION DATE: 2065
PROJECT MANAGER: Keith Watson